July 21, 2010
This project is now complete. Carpeting was completed by the end of June. Painting was completed the week of July 19th.
June 2010 -
Update forthcoming.
May 2010 -
This project started May 17, 2010 with removing of carpet. Painting and carpeting crews will work around conferences to complete this project.
April 2010 -
During summer 2010, Witmer Residence will be receiving a facelift. Starting May 17, 2010, the contractor will be installing new carpeting in all residence rooms and common areas and painting these areas will take place at the same time.
|
|
|
|
|
|