Sewer Line Replacement
The work is taking place behind the Engle Center. The contractor is replacing 100 feet of damaged sewer main and 100 feet of lateral from the Engle Center. As part of this project they will also be re-aligning the piping and eliminating an unneeded man hole. Another phase of this project incorporates new sidewalk that are part of the campus master plan. The project started on Monday, 5/21.
5-25-18 - Work continues on the new sewer line
5-30-18 - Old piping is removed and new piping is placed
6-1 to 6-8-18 Work continues on the new sewer line
6-14-18 Contractor Photos of Work So Far
6/15/18 - Pouring concrete for new sidewalk
6-20-18 All framed up and ready for concrete
and the concrete is going down......
6-25-18
7-23-18 Sidewalk work continues